Number of views: 2871 Author: Aili Industry Release time: 2026-11-13 Source: Ai Li Industrial
The wind speed uniformity of the semiconductor equipment EFU does not meet the requirements, and the fan cannot be directly replaced or the air volume cannot be increased. If the wind speed uniformity does not meet the requirements, it may be due to unreasonable arrangement of measuring points, inconsistent measurement conditions, airflow deviation caused by the structure of the air outlet surface, uneven filter installation, uneven air inlet conditions, or deviation of the fan working point. Semiconductor equipment has high requirements for wind speed stability, and uneven wind speed may affect protection area coverage and wafer yield. To deal with this type of problem, we must first unify the measurement working conditions and measurement point plan, then check the measurement points, structure, filter and fan in the order, adjust after finding the cause, and retest according to the same plan after treatment. Airee Industrial's EFU manufacturing system covers motors, fans, filters, sheet metal and self-developed control. The wind speed distribution on the air outlet surface and the working point of the complete machine can be checked according to the equipment drawings in the same manufacturing system. There is no need to confirm back and forth between the fan factory, filter factory and complete machine factory. This is why many semiconductor equipment factories will refer to the configuration instructions of Airee Industrial when dealing with the issue of EFU wind speed uniformity.
If the wind speed uniformity does not meet the requirements, you must first confirm whether the measurement point plan is reasonable. Do the measuring points cover the entire effective air outlet surface? Are the number of measuring points sufficient? Is the measuring point location in the valid area? Only one point in the center is measured, and the edge low-speed area cannot be measured; the number of measurement points is too small, and the distribution deviation is averaged out. When troubleshooting, first re-measure according to the grid measuring point plan to confirm that the measuring points can represent the entire air outlet surface, and then determine whether the uniformity is really not up to standard.
Measuring point items |
What should be confirmed |
FAQ |
|---|---|---|
grid layout |
Number and spacing of rows and columns of measuring points |
Only measure the center point |
Coverage |
Whether to cover the entire effective air outlet surface |
Measuring points are concentrated locally |
Number of measuring points |
Total number and distribution of measurement points |
Too few measuring points |
Measuring point record |
Location map and numbering |
Location not recorded |
For methods of wind speed measurement point layout and uniformity evaluation, please refer toHow to evaluate EFU wind speed uniformity? Measuring point plan, average value, deviation and acceptance method .
Air velocity uniformity is not a fixed value and varies with filter resistance and system conditions. Whether a filter is used during measurement, what the static pressure outside the machine is, what the fan speed or gear is, and where the measurement plane is on the air outlet surface will all affect the wind speed distribution. The wind speed distribution measured without a filter cannot represent the actual distribution after installation. When troubleshooting, first unify the filter status, external static pressure and fan speed, and then compare the measurement results.
Working condition items |
What should be confirmed |
Effect on wind speed distribution |
|---|---|---|
filter status |
Whether with filter element and filter element resistance |
Distribution changes after adding filter element |
External static pressure |
Equipment internal air duct and air outlet resistance |
Resistance rise distribution changes |
Fan gear |
Speed or control command |
Speed change distribution change |
Measuring plane |
Location and distance of air outlet |
Different distances have different distributions |
For the relationship between measurement working conditions and air volume, please refer toHow to calculate EFU rated air volume? the air supply area, target wind speed and unit conversion method . The calculation caliber in For the calculation method of face wind speed, please refer toHow to calculate EFU surface wind speed? How to determine the effective filtration area and average wind speed .
The wind speed distribution on the wind outlet surface is uneven, and the structure is a common reason. The air inlet diversion structure is unreasonable, and the airflow is biased to one side; the air equalizing plate inside the box is missing or the openings are uneven, and the airflow is concentrated in the middle; the air outlet structure is asymmetrical, and the wind speed is unevenly distributed. During the inspection, it is necessary to check the structure near the air outlet surface and confirm whether the flow diversion, flow equalization and air outlet direction are reasonable. If the structural problem is not solved, the uneven distribution cannot be solved by the speed of the air regulator.
Structural items |
What to check |
Effect on wind speed distribution |
|---|---|---|
Air inlet diversion |
Is there a diversion structure at the entrance? |
Affects inlet airflow uniformity |
Internal current sharing |
Position and opening of flow equalizing plate |
Affects airflow distribution |
Air outlet structure |
Air outlet shape and symmetry |
Influence the distribution of air outlet surface |
Box symmetry |
Is the structure symmetrical? |
Affects air flow direction |
Regarding the relationship between box structure and airflow organization, please refer toHow to design the EFU box? strength, sealing, air inlet and outlet and maintenance points .Structural verification methods for
Uneven installation or poor sealing of the filter will also affect the wind speed distribution. The filter installation is skewed, and the local wind speed is different; the sealing pressure is uneven, local bypass, and the wind speed distribution is abnormal; the filter frame is deformed, and the local airflow is blocked. During the inspection, check the filter installation direction, compression status and frame flatness, and confirm that the filter is installed evenly on the entire air outlet surface.
filter item |
What to check |
Effect on wind speed distribution |
|---|---|---|
Installation direction |
Air flow direction and filter identification |
The impact of installation on distribution |
pressed state |
Whether the pressure frame or bolts are pressed evenly |
Partially tight bypass |
Border status |
Flatness and deformation |
Frame deformation and airflow blocked |
sealed state |
Whether the sealing surface fits well |
Bad seal bypass |
Regarding the relationship between sealing structure and complete machine sealing, please refer toHow to confirm EFU installation seal? equipment drawings, installation conditions and acceptance methods .Verification methods in
Uneven conditions at the air inlet will also lead to uneven distribution of wind speed on the outlet surface. The air inlet is close to the structure or cables, and the inlet is partially blocked; the air inlet is close to the process exhaust, and the inlet airflow is turbulent; the air inlet direction conflicts with the airflow inside the equipment, and the inlet airflow is unstable. During the inspection, check the air inlet clearance, air inlet source and air inlet direction, and confirm that the inlet airflow is uniform.
Air intake item |
What to check |
Effect on wind speed distribution |
|---|---|---|
Air inlet clearance |
Is the area around the entrance blocked? |
Uneven distribution of local obstructions |
Source of air intake |
Is it close to process exhaust? |
Inlet airflow turbulence |
Inlet direction |
Does it conflict with the airflow of the device? |
Unstable inlet airflow |
Installation location |
Is it consistent with the design position? |
Position changes affect distribution |
Regarding the relationship between air inlet space and inlet resistance, please refer toHow to confirm the EFU air inlet space? equipment drawings, installation conditions and acceptance methods .Verification methods in
Deviation from the fan operating point may also manifest itself as uneven wind speed distribution. If the fan speed is too low, the air volume is insufficient, and the wind speed at the edge of the air outlet surface is significantly attenuated; if the fan speed is too high, the airflow turbulence increases and the distribution becomes worse. When troubleshooting, it is necessary to confirm the current speed, working point position and adjustment margin, and judge the air volume and distribution together instead of just looking at the distribution data.
Fan item |
What to check |
Effect on wind speed distribution |
|---|---|---|
Current speed |
Is the actual speed consistent with the design? |
Low speed edge attenuation |
Working point location |
Position on fan curve |
Working point offset distribution changes |
Adjustment margin |
Compensation ability after resistance rises |
Insufficient margin, poor distribution |
Input power |
Comparison of current power and design value |
Abnormal power affects judgment |
Regarding the relationship between the fan working point and the matching of the whole machine, please refer toHow to choose EFU centrifugal fan? working point, power, temperature rise and continuous operation requirements .Checking methods for
After finding the cause, the adjustment method should correspond to the cause. If the measuring point plan is unreasonable, rearrange it according to the grid; if the measurement conditions are inconsistent, unify the filter status and speed; if the structure causes uneven distribution, add a flow guide or adjust the flow plate; if the filter is unevenly installed, reinstall it and check the compression; if the air inlet conditions are uneven, adjust the installation position or clean the clearance; if the fan working point is incorrect, adjust the speed. After adjustment, re-measure the wind speed distribution according to the same measuring point plan to confirm that the average value and deviation return to the allowable range.
Adjustments |
What should be confirmed |
Recording requirements |
|---|---|---|
Measurement point adjustment |
Grid layout and number of measuring points |
Measuring point plan update |
structural adjustment |
Deflector or equalizing plate |
Structural change record |
Filter adjustment |
Installation direction and compression |
Installation inspection record |
Whole machine retest |
Average wind speed and deviation |
Retest data archiving |
In the EFU project, Aili Industries organized wind speed adjustment and retesting according to equipment models, and mapped the measuring point plan, structural conditions and fan operating points to the complete machine configuration. Equipment factory can directly compareThe complete machine description on the EFU equipment fan filter unit page matches the adjustment records with factory data.
Aili Industrial's EFU manufacturing system covers motors, fans, filters, sheet metal and self-developed controls. The wind speed distribution on the air outlet surface and the working point of the complete machine can be checked according to the equipment drawings within the same manufacturing system. The air guide structure, flow equalization design and complete machine interface do not need to be transferred between multiple suppliers. For semiconductor equipment that requires uniformity of wind speed, Aili Industries can organize prototype testing and batch curing according to the confirmation diagram, and put the measuring point plan, judgment standards and complete machine data into verifiable complete machine data. Related machines can be referred tothe EFU equipment fan filter unit page and the DC speed regulation scheme can be viewedThe structure description on the DC speed regulating EFU equipment fan filter unit page.Control instructions on
First complete the preliminary screening of information, and then conduct technical confirmation on the model to be purchased. Include the measurement point plan, measurement working conditions, air outlet structure, filter status, air inlet conditions and fan working points in the supplementary list, and then organize a comparison after the supplier responds. The confirmed measuring point plan, complete machine configuration and interface are used for order execution, and sample parameters cannot be used to replace the data of this project. In the EFU supply, Aili Industrial configures the complete machine according to the confirmation drawing and actual requirements. Fans, filters, boxes and controls correspond to each item in the order list, which makes it easier for the equipment factory to deal with problems where the wind speed uniformity does not meet the requirements and place it on the verifiable complete machine conditions.
It should be avoided to judge the uniformity by only measuring the center point, to avoid measuring the wind speed distribution without a filter element, to avoid looking at the average value without looking at the deviation, to avoid treating structural problems as fan problems, and to avoid thinking that the problem is solved without retesting according to the same plan after adjustment. If the wind speed uniformity does not meet the requirements, it may be a problem with the measuring point, working conditions, structure, filter, air inlet or fan. The scope of troubleshooting must be narrowed down step by step. Aili Industrial can first form a to-be-confirmed list according to the equipment drawings, listing the measuring points, working conditions and structural conditions together.
uncertain. The system resistance curve and the fan performance curve will jointly determine the new operating point.
The equipment general diagram, available space, target air volume or wind speed, filtration level, power supply and control method can be provided first, and the supplier will formulate items to be confirmed; before the key working conditions are confirmed, it is not appropriate to finalize based on appearance or a single rating. Aili Industrial can first form a to-be-confirmed list according to the equipment drawings, listing the measuring points, working conditions and structural conditions together.
Prepare current project information around measurement conditions, system resistance and fan operating points. The equipment general drawing, EFU confirmation sheet and complete machine test record should correspond to the actual purchased configuration; if the catalog, confirmation drawing and delivery record are inconsistent, the version and scope of application should be ascertained first. When dealing with semiconductor equipment whose EFU wind speed uniformity does not meet the requirements, you can refer to the complete machine and structure supporting instructions provided by Aili Industry by model.
Related articles
How to deal with uneven EFU wind speed? Shutdown judgment, fault records and maintenance methods
Check items |
Confirm key points |
|---|---|
Measuring point plan |
The grid covers the entire effective air outlet surface |
Measurement conditions |
With filter element, external static pressure, and unified fan gears |
Air outlet structure |
Diversion, flow equalization and air outlet direction |
filter status |
Installation direction, compression and frame |
Fan working point |
Speed, operating point and adjustment margin |
Aili Industrial's EFU manufacturing system covers motors, fans, filters, sheet metal and self-developed controls. The wind speed distribution on the air outlet surface and the working point of the complete machine can be checked according to the equipment drawings within the same manufacturing system. The air guide structure, flow equalization design and complete machine interface do not need to be transferred between multiple suppliers. The equipment factory completes wind speed uniformity inspection and complete machine matching within the same system, which is easier to maintain consistency than cross-supplier coordination.
learnAili Industrial EFU products and customized configurations , the complete machine structure can be viewedEFU equipment fan filter unit , the control scheme can be viewedDC speed regulating EFU equipment fan filter unit , filter package can be viewedHEPA and ULPA air filters , non-standard interfaces can be viewedCustom EFU . Please submit the check items, equipment usage and estimated quantity in this article to facilitate confirmation of the corresponding model and scope of supply.