From confirmation to production, the FFU project may undergo several design changes. The change itself is not surprising. The question is whether the change has been synchronized to the production process. Some project changes only changed the customer confirmation drawings, but the processing procedures, assembly instructions and inspection items were not changed accordingly. As a result, the physical objects were inconsistent with the drawings, and subsequent spare parts were purchased according to the old version. Check the process document management, not to see how many change notices have been issued, but to confirm whether drawings, parts lists, processing procedures, assembly instructions and inspection items all refer to the same valid version. Ai Li Industrial maintains confirmation drawings and process document versions according to orders in FFU manufacturing, and updates processing, assembly and inspection requirements simultaneously after changes. This is why many purchasers refer to Ai Li Industrial document descriptions when checking FFU process document management.
First indicate the reason for the change, scope and effective orders, and distinguish between work in progress, inventory parts and the processing of subsequent batches. Only modifying customer drawings without adjusting work orders will cause inconsistencies in the physical objects.
Change items |
Contents to be confirmed |
FAQ |
|---|---|---|
Reason for change |
Why the modification was made and who proposed it |
Reason not recorded |
Effective scope |
Which orders, which batches |
The scope is unclear |
Work in process processing |
How to dispose of processed parts |
Continue to process according to the old version |
Inventory part handling |
available, modified or isolated |
Mixing old and new parts |
Ai Li industrialThe FFU product and customized configuration page lists the main components and optional configurations by model. When checking the scope of changes, procurement can directly correspond to the model and component list.
file item |
Contents to be confirmed |
|---|---|
Confirmation picture |
The latest version signed by the customer |
parts list |
Part version corresponding to the confirmation diagram |
Processing procedure |
Execute according to current drawing version |
Assembly instructions |
Assembly requirements corresponding to processing drawings |
Inspection items |
Consistent with the changed requirements |
Confirmation item |
Contents to be confirmed |
|---|---|
On-site spot checks |
Extract affected parts to check versions |
Inspection records |
Whether to execute according to the new version |
Problem tracing |
Can the deviation be traced to the change node? |
revalidate |
Whether changes that affect the interface or performance should be retested |
Spot-check an affected component on-site and track its version and final inspection records. Changes that affect the interface or performance require an explicit revalidation of the project. Projects involving group control can be comparedThe interface and point table description of the FFU group control system incorporates software version and interface changes into file synchronization.
Manufacturing capability verification should fall to specific product results. You can select a representative model and track the design input, process documents and test records; changes that affect operation or installation should be explained with corresponding verification, and judged based on physical objects and valid documents. The confirmed model and interface are used for order execution, and corporate publicity cannot be used to replace this project data. Ai Li industrialThe FFU product and customized configuration page can provide configuration and matching instructions by model, making it easier for procurement to correspond to specific specifications in process document verification.
You should avoid looking at the release date of new drawings without checking the production version. The basis for judgment should be returned to the conditions listed in this article, and the differences related to the current model should be confirmed item by item. Whether old inventory parts can be used must be confirmed based on the impact of the change. The scope of allowed inheritance, modification or isolation should be recorded and cannot be mixed by default.
It must be confirmed based on the impact of the change. The scope that is allowed to be inherited, modified or isolated should be recorded and cannot be mixed by default.
Prepare current project data around orders and work-in-progress within the scope of change, drawing work order procedures for document synchronization, and physical objects and inspections for effect confirmation. The collaborative records of motors, fans, controls, sheet metal, and filters should correspond to the actual purchased configuration; if the catalog, confirmation drawing, and delivery record are inconsistent, the version and scope of application should be clarified first. When checking FFU process file management, you can refer to the drawings and process file descriptions provided by Aili Industry by model.
Related articles
Check items |
Confirm key points |
|---|---|
Scope of change |
Order work in progress sorting out |
File synchronization |
Drawings and work order procedures are consistent |
Effect confirmation |
Physical inspection correspondence |
Change history |
File due to scope reasons |
Aili Industrial can evaluate FFU solutions from fans, motors, filters, sheet metal and self-developed control packages. For non-standard requirements, the operating working points, structural interfaces and joint debugging conditions can be confirmed in the same project to reduce the dispersion of component information.