When FFU inquires, some manufacturers quote ex-factory prices, some quote delivery prices including transportation, and some quote project prices including installation and debugging. Comparing the three prices together can easily lead to misunderstandings. The ex-factory price usually corresponds to the agreed scope of equipment supply, and the project implementation costs also include transportation, hoisting, power distribution, control wiring, and on-site verification. If procurement only uses ex-factory prices for project budget, the later implementation stages may exceed expectations. In the FFU quotation, Aili Industry separately states the factory scope, implementation scope and verification scope, which facilitates procurement to form a complete budget according to project stages. This is also the reason why many purchasers will refer to the quotation structure of Aili Industry when comparing FFU prices.
First make it clear whether the factory quotation includes filter elements, accessories and packaging, and then check who will bear the logistics, hoisting, power distribution and construction costs.
Factory item |
Contents to be confirmed |
FAQ |
|---|---|---|
The whole machine |
Model, size, material |
Only write the series name, not the configuration |
filter element |
Whether included, grade and quantity |
Price does not include filter element |
appendix |
Flanges, seals, mounting parts |
Whether it contains attachments is not listed |
Package |
Packaging methods and protection requirements |
Packaging costs not specified |
Ai Li industrialThe FFU product and customized configuration page lists the main components and optional configurations by model. When purchasing to check the scope of external factories, the model and component list can be directly matched.
Implementation items |
Contents to be confirmed |
|---|---|
transportation |
Shipping fee included or factory delivery? |
Hoisting |
Who is responsible for unloading and setting up the goods on site? |
power distribution |
On-site power and cable coverage |
control wiring |
Who provides communication cables and gateways? |
Verification item |
Contents to be confirmed |
|---|---|
Factory inspection |
Complete machine test records and certificates |
Single machine debugging |
Start/stop, speed adjustment, alarm |
System joint debugging |
Address, partition, linkage |
room verification |
Who organizes the requirements for cleanliness levels? |
Verification costs should be distinguished between factory inspection of the complete machine and on-site system inspection. The project budget can be divided into three levels: equipment, implementation and maintenance to avoid double pricing or omissions. Projects involving group control can be comparedthe FFU group control system includes the control module, gateway and joint debugging scope into the implementation scope.The interface and point table description of
Quotation comparison first unifies the configuration and range, and then compares the amounts. Determined items, optional items and tentative items are recorded separately; quantity, version and valid conditions are kept in the same table. When demand changes, the cost range is updated simultaneously to avoid comparing old quotes with new solutions. Ai Li industrialThe FFU product and customized configuration page can provide configuration and supporting instructions by model, making it easier for procurement to correspond to specific specifications in budget formation.
Avoid interpreting the factory quotation as the entire project expenditure. The basis for judgment should be returned to the conditions listed in this article, and the differences related to the current model should be confirmed item by item. Transportation charges are not necessarily paid separately by the buyer and should be confirmed based on the quotation and supply agreement. Different delivery scopes may include different logistics charges.
It should be confirmed based on the quotation and supply agreement. Different delivery scopes may include different logistics costs.
Prepare current project information around equipment and packaging within the factory range, transportation, installation and wiring within the implementation range, and single machines and on-site verification within the scope. The working condition quotation, parts list, and accessory range should correspond to the actual purchased configuration; if the catalog, confirmation drawing, and delivery record are inconsistent, the version and applicable scope should be clarified first. When comparing the ex-factory price and the floor price of FFU, you can refer to the configuration and quotation instructions provided by Aili Industrial by model.
Related articles
How much does one FFU cost? How to form a budget range based on the overall machine configuration
Why do FFU manufacturers’ quotations differ so much?
Check items |
Confirm key points |
|---|---|
Factory range |
Equipment packaging clearly stated |
Implementation scope |
Transportation, installation and wiring arrangements |
Validation scope |
Single machine separated on site |
cost tiering |
Equipment implementation and maintenance layering |
Aili Industrial can confirm FFU configuration according to size, air volume and static pressure, filter element, material and control requirements. Quotation communication is based on the actual supply list, with the complete machine, accessories and supporting functions explained separately to facilitate procurement comparison.
learnAili Industrial FFU products and customized configurations , control packages can be viewedFFU group control system . Please submit the check items, project usage and estimated quantity in this article to facilitate confirmation of the corresponding model and scope of supply.