High-efficiency air supply outlets are usually installed on the ceiling of clean rooms as the end air supply equipment of centralized air treatment systems.
During installation, not only do you need to fix the box to the ceiling, but you also need to handle:
Site dimensions → Ceiling opening → Box fixing → Air duct connection → Sealing → Internal cleaning → HEPA/ULPA filter installation → System debugging
Among them, size matching, interface sealing, installation cleanliness and filter protection are several aspects that need to be focused on during the installation process.
Relevant clean room construction requirements also emphasize that the size of the air outlet of the high-efficiency filter should meet the design requirements and should be cleaned before installation. The joint between the air outlet and the ceiling needs to be sealed. After the air outlet is installed, it should be connected to the air duct in time and the opening should be protected.
The common installation process of high-efficiency air supply vents can be summarized as:
On-site confirmation → Dimension check → Ceiling opening → Box hoisting → Horizontal adjustment → Box fixing → Air duct connection → Seam sealing → Box cleaning → HEPA/ULPA filter installation → Inspection and debugging
In actual projects, the specific construction sequence needs to be determined based on the clean room structure, air supply outlet structure and construction organization arrangements.
Before installation, you first need to confirm the location of the air supply outlet according to the clean room design drawings.
Main confirmations:
Check items |
What needs to be confirmed |
Impact on installation |
On-site focus |
|---|---|---|---|
Air outlet position |
floor plan |
Determine the location of the opening |
Avoid conflicts with devices |
Ceiling size |
Module size |
Affect box installation |
confirm opening |
Duct location |
Top air intake/side air intake |
Affects interface direction |
Confirm in advance |
Number of air outlets |
Design quantity |
Affects air supply layout |
Check with design |
maintenance space |
Filter replacement space |
Affect later maintenance |
Reserve in advance |
Luminaire location |
Lamps and other equipment |
Affect ceiling layout |
avoid interference |
It is not possible to directly drill holes for installation without confirming the on-site dimensions.
The size of the high-efficiency air supply vent box, filter size and ceiling opening size need to match each other.
It is recommended to check before installation:
Overall size of air supply outlet + installation size + ceiling module size + filter size + air duct interface size
If customized products are used, further verification is required:
Box length, width and height
Flange size
Top air inlet interface
Side air inlet interface
filter size
Installation hole position
boom position
Relevant construction information also requires that the size of the air supply outlet of the high-efficiency filter meets the design requirements.
A visual inspection should be done first.
Check items |
Check content |
What to do when problems are discovered |
|---|---|---|
cabinet |
Is it deformed? |
Pause installation and confirm |
surface |
Is the coating complete? |
Confirm whether it affects the installation |
flange |
Is it deformed? |
Check connection conditions |
Air inlet interface |
Is it complete? |
Confirm duct connection |
filter |
Is the packaging complete? |
avoid damage |
Seals |
Is it complete? |
Confirm sealing structure |
Product size |
Is it consistent with the drawings? |
Reconfirm before installation |
If the cabinet has been significantly deformed or the interface is damaged, it should be processed first and should not be installed directly.
according toof the high-efficiency air supply outlet is determined on the clean room ceiling panel.The actual installation size
The typical process is:
Measure → Position → Mark → Open → Clean the opening → Check size
Special attention is needed here:
Don't simply drill holes according to a certain fixed amount.
There may be size differences in different ceiling systems, air outlet structures and installation methods. The actual product installation dimensions and project construction drawings should prevail.
Install the high-efficiency air supply box to the ceiling opening.
It can usually be installed using booms, hangers, or fixed structures designed for the project.
Need to adjust during installation:
Cabinet height → Level → Flange position → Ceiling plane
Generally, it is necessary to make the lower edge of the air supply port and the clean room ceiling form a reasonable match.
Do not allow the filter or box to bear unreasonable structural loads during installation.
After the box is fixed, connect the air duct according to the air inlet structure.
Typical connection method:
Main air duct → Branch air duct → Top interface → High-efficiency air supply outlet
Typical connection method:
Main air duct → Branch air duct → Side interface → High-efficiency air supply outlet
The specific connection form needs to be determined according to the circular interface, square flange interface or other structures.
After the connection is completed, you need to check:
Whether the interface matches
Is the fixation firm?
Is the seal continuous?
Is there any obvious risk of air leakage?
Does the air duct produce additional pulling force on the box?
The clean room construction requirements also emphasize that the air supply outlet should be connected to the air duct after installation, and the opening should be protected and sealed.
When installing high-efficiency air supply vents, the joint between the box and the clean room ceiling is a location that needs to be focused.
The typical structure can be understood as:
Air supply flange→Sealing material→Clean room ceiling panel
The purpose of sealing is to reduce the possibility of untreated air bypassing the installation gap and entering the clean room.
Therefore, after installation you need to check:
Flange joint → surrounding seal → interface seal → ceiling panel connection
If obvious gaps are found, they should be processed according to the project construction requirements.
Relevant specification information also clearly states that the joint between the air outlet flange and the ceiling panel needs to be sealed.
The sooner a high-efficiency filter is installed, the better.
During the clean room construction process, efforts should be made to avoid prolonged exposure of the filter to the dust environment.
Before installing the filter, you need to confirm:
project |
Check content |
|---|---|
Filter model |
Matches the air outlet |
Overall dimensions |
Matches the installation frame |
Sealed structure |
Matches the air supply structure |
filter material |
Is it complete? |
frame |
Is it deformed? |
sealant |
Is there any obvious damage? |
Package |
Is it complete? |
Installation direction |
Confirm according to product requirements |
Relevant construction requirements also emphasize that clean rooms and related technical mezzanines and suspended ceilings should be cleaned and wiped before installation of high-efficiency filters.
the high-efficiency filter is installed, you need to check:After
Filter position → Sealing structure → Pressed state → Installation direction → Peripheral seams
If the project has on-site leak detection requirements, leak detection and confirmation will be carried out according to the project acceptance plan.
Things to note here:
The installation of the filter is completed≠ The installation of the entire air supply system is completed.
Also needs to be combined with:
Duct system
Air volume
static pressure
filter resistance
Clean room airflow organization
Cleanliness test
Make overall confirmation.
FAQ |
Possible reasons |
suggestion |
|---|---|---|
Air outlet size does not match |
Failure to check dimensions before drilling |
Check drawings and actual objects before installation |
Cabinet tilt |
The boom is not adjusted properly |
Reset fixed |
Air duct connection is not tight |
Insufficient interface or sealing |
Check connections and seals |
Air leakage around ceiling |
Flange seams are not treated |
Sealing according to construction requirements |
Filter contamination |
Premature unpacking and installation |
Minimize exposure time |
Filter damage |
Improper handling or installation |
Handle with care |
Unable to maintain later |
No replacement space reserved |
Confirm maintenance direction before installation |
Conflict between air outlet and lamps |
Insufficient on-site positioning |
Comprehensive arrangements in advance |
Air duct pulls box |
Inadequate duct support |
Air duct independent support |
Uneven air supply |
System design or tuning issues |
Check air volume and airflow organization |
HEPA and ULPA filters are precision filtration components and should be avoided during installation:
impact
extrusion
Scratched filter media
Disassemble at will
prolonged exposure
Construction that generates large amounts of dust is carried out near the filter
Filter transportation and storage should also be carried out in accordance with the manufacturer's requirements to avoid severe vibration and collision.
After the installation is completed, it is not recommended to just check 'whether the air vent is installed'.
Systematic installation checks should be carried out.
You can follow:
Appearance inspection → Box inspection → Air duct inspection → Seal inspection → Filter inspection → Air volume debugging → System inspection → Cleanliness verification
conduct.
Specific testing items and acceptance standards should be based on project design documents, contract technical requirements and applicable standards.
Typical air path:
Air duct → Top air inlet interface → Static pressure box → HEPA/ULPA → Clean room
Focus on:
Head space + duct height + ceiling height + maintenance space
Typical air path:
Air duct → Side air inlet interface → Static pressure box → HEPA/ULPA → Clean room
Focus on:
Side air duct position + interface space + ceiling structure + maintenance space
Therefore, although the basic process of the installation method is similar, the interface direction and on-site size confirmation are different.
Produced by Aili IndustrialHigh-efficiency air supply vents can be matched in structure, size, air inlet mode and filter configuration according to project requirements.
In the project selection stage, you can first confirm:
Cleanliness level → Room size → Design air volume → Number of air outlets → Ceiling size → Air duct direction → HEPA/ULPA specifications → Installation and maintenance space
Then determine the specific air supply outlet plan.
Aili Industrial also has high-efficiency air supply vents, HEPA/ULPA filters, FFU, EFU, fans, motors, control systems and sheet metal structures and other products and supporting production capabilities.
For projects that require overall clean room air treatment, high-efficiency air supply outlets and high-efficiency filters can be combined for terminal air supply; for equipment-level or local clean applications, FFU, EFU and other products can also be selected according to space conditions.
This product matching capability can reduce the matching problems between different equipment in terms of size, filter and installation interface. The specific solution is still subject to the project design and site conditions.
If you need to quickly understand how to install high-efficiency air supply vents, you can remember:
On-site confirmation → Dimension check → Ceiling opening → Box hoisting → Horizontal adjustment → Fixed box → Connect air duct → Seam sealing → Clean box → Install HEPA/ULPA → Inspection and debugging
The ones that require the most attention are:
Dimensional matching, box fixing, air duct connection, sealing, filter protection and post-installation system inspection.
It is usually carried out in the order of on-site positioning, size verification, ceiling opening, box fixing, air duct connection, sealing treatment, internal cleaning, HEPA/ULPA filter installation and system inspection.
Most ceiling installation projects require reliable independent support or hoisting structures. The specific use of booms, hangers or other fixing methods should be determined according to the product structure and project construction plan.
Connect according to the top air inlet or side air inlet structure adopted by the air supply outlet, as well as the specific forms such as circular interface and flange interface, and do a good job of fixing and sealing.
need. The air outlet flange and ceiling panel should be sealed according to project construction requirements to reduce bypass air leakage.
Usually, you should try to install it after cleaning the clean room and related areas, and avoid long-term exposure of the filter to the construction dust environment.
need. Air supply outlets, installation areas and related suspended ceilings or technical mezzanines should be cleaned according to the clean construction requirements of the project.
Ordinary mechanical installation can be carried out in accordance with the manufacturer's installation instructions and project construction plan, but the clean room project also involves air ducts, seals, filters and system debugging. It is recommended that it be completed by professionals with experience in clean room construction.
Whether and how testing is required depends on the project design, acceptance criteria, and filter seal construction. For projects with clear leak detection requirements, the corresponding detection plan should be implemented.
The installation of high-efficiency air supply vents is not simply fixing the box on the ceiling, but a positioning, size matching, box installation, air duct connection, sealing, filter installation and system debugging .complete process including
The most basic installation path can be summarized as:
Design confirmation → On-site measurement → Air outlet positioning → Box installation → Air duct connection → Sealing treatment → Cleaning → HEPA/ULPA installation → System debugging
If it is an Aili industrial high-efficiency air supply vent project, it is recommended that the air vent size, filter specifications, air inlet direction, ceiling size, air duct location and maintenance space be clearly confirmed during the product procurement stage, so that the product can better match the on-site installation conditions of the clean room.
Aili Industrial can assist in confirming the product specifications and installation conditions of high-efficiency air supply vents based on the information provided by the project.
It is recommended to prepare:
Clean room floor plan + ceiling size + air duct location + design air volume + HEPA/ULPA specifications + installation height
Based on this information, we can further determine whether top air inlet or side air inlet, air supply outlet size, filter specifications and installation interface。