The owner directly purchases FFU, which seems to eliminate a layer of intermediate links. In fact, the responsibility for interface coordination is placed in his own hands. The manufacturer is responsible for supplying the equipment, the construction unit is responsible for installing the equipment, the designer is responsible for the system conditions, and each of the three parties is responsible for a section. If the owner does not actively organize technical docking, it is easy for the manufacturer to produce according to his own drawings, the construction party to install according to his own habits, and the designer's conditions are not implemented. In the FFU project, Aili Industrial can provide size, weight, power supply and control data for specific models, and cooperate with the owner to complete the interface confirmation with the construction unit and designer. This is one of the reasons why many owners choose Aili Industrial FFU.
The designer confirms the cleanliness target and system conditions, the manufacturer submits the size, weight, power supply and control information of the complete machine, and the construction unit checks the accessibility of the ceiling, power distribution and maintenance. These three types of inputs must be exchanged before equipment is scheduled, otherwise the cost of subsequent changes will be very high.
Participants |
Content should be provided |
Common omissions |
|---|---|---|
designer |
Cleanliness level, working conditions, system conditions |
Only the target is given, not the installation conditions. |
factory |
Dimensions, weight, power supply, control interface |
Only samples will be given, no confirmation pictures will be given |
construction unit |
Ceiling, power distribution and maintenance conditions |
Only the installation fee is quoted, no interface requirements are mentioned |
owner |
Organization confirmation and clear division of responsibilities |
Thinking that the purchase is over |
Ai Li industrialThe FFU product and customized configuration page can provide size, weight and control interface descriptions by model. Owners can directly quote these information as the basis for discussion when organizing three-party docking.
Direct procurement does not mean that all interface responsibilities are automatically transferred to the construction party. The owner should organize the three parties to form a written record of design input, installation input and acceptance responsibilities. The interface table should at least include the following:
interface item |
Contents to be confirmed |
|---|---|
mechanical interface |
Shape, opening, support, sealing method |
Electrical interface |
Voltage, wiring method, terminal definition |
control interface |
Communication protocol, point table, linkage method |
Maintenance interface |
Filter element replacement path and maintenance space |
Division of labor for acceptance |
Single machine inspection, installation inspection, system verification |
Before the equipment is scheduled, confirm the supply scope of the fixing method, sealing materials and control cables. If the on-site conditions change, the drawings should be revised simultaneously, and no unilateral verbal adjustments should be made. What matters must be confirmed before production, mainly including appearance, openings, supports, maintenance paths, power supply and control interfaces. Changes will affect the complete machine and on-site matching. Projects involving group control can be comparedThe interface and point table description of the FFU group control system , write the address planning and wire range into the interface table.
Installation guidance and on-site commissioning are different services, and the supply instructions should clearly indicate the delivery method and work content. When organizing acceptance, owners should also arrange equipment acceptance and room cleanliness verification separately.
Acceptance type |
Organizer |
in accordance with |
|---|---|---|
Stand-alone function check |
Manufacturer cooperation |
Whole machine test record and control function |
Installation quality inspection |
construction unit |
Interface table, installation record |
System joint debugging |
owner or general contractor |
Control point table, linkage test |
Room cleanliness verification |
third party or designer |
Cleanliness level requirements |
Aili Industrial can provide complete machine test records and control function descriptions in FFU supply, cooperate with the owner to complete the single machine function inspection process, and help the three parties reduce repeated confirmations during the acceptance stage.
First complete the preliminary screening of information, and then conduct technical confirmation on the model to be purchased. Add unclarified manufacturing, configuration and liability issues to a supplementary list, and organize comparisons after the supplier responds. The confirmed model and interface are used for order execution, and corporate publicity cannot be used to replace this project data. It is recommended that the owner form a three-party interface table, listing the data provider, installation completion party and acceptance organizer, and save it as an attachment to the contract. Ai Li industrialThe FFU product and customized configuration page can provide size, control and matching instructions by model, making it easier for owners to check product information simultaneously during the interface confirmation stage.
It should be avoided to think that the construction party will automatically assume all equipment interfaces after direct procurement. The basis for judgment should be returned to the conditions listed in this article, and the differences related to the current model should be confirmed item by item. Installation guidance and on-site commissioning are different services, and the supply instructions should clearly indicate the delivery method and work content.
It mainly includes the shape, openings, supports, maintenance paths, power supply and control interfaces. Changes will affect the complete machine and on-site matching.
Prepare the current project information around the cleanliness and working conditions of the design input, the loading and wiring of the installation input, and the jointly confirmed interface table and sign-off. The manufacturing site, configuration confirmation form, and complete machine test records should correspond to the actual purchased configuration; if the catalog, confirmation drawing, and delivery record are inconsistent, the version and scope of application should be clarified first. When checking the FFU product configuration, you can refer to the dimensions and control interface descriptions provided by Aili Industry by model.
Check items |
Confirm key points |
|---|---|
design input |
Cleanliness and working conditions |
Installation input |
Load carrying and wiring requirements |
Interface signature |
The responsibilities of the three parties are clear |
Division of labor for acceptance |
Separate stand-alone machine and system |
Aili Industrial's FFU manufacturing system covers motors, fans, control systems, sheet metal, filters and complete machine assembly. Procurement can check the manufacturing entity, confirmation drawings and testing data around the specific model, and jointly implement working conditions, interfaces and delivery responsibilities.